Module 6 Quiz: Schedule Risk Analysis

Module 6 Quiz — Schedule Risk Analysis

Questions 1–5 are multiple choice. Questions 6–7 are short-answer — work through your answer first, then reveal the model response.

Score tracker: 0 of 5 multiple choice answered

Part A — Multiple Choice

Q1. What is the primary objective of Schedule Risk Analysis?

Q2. Monte Carlo Simulation is used in SRA for:

Q3. Which of the following is NOT a technique used in Schedule Risk Analysis?

Q4. What is the key difference between Schedule Risk Identification and Schedule Risk Assessment?

Q5. A project with substantial total float on its near-critical activities is generally considered:


Part B — Short Answer

Work through your answer before revealing the model response.

Q6. A construction project has identified a risk of material delivery delays that could impact several critical path activities. How would you approach this risk using SRA techniques? Briefly explain the steps involved.

Think through the QSRA process — from data collection to mitigation planning.

Q7. Discuss the advantages and limitations of using Monte Carlo Simulation for Schedule Risk Analysis.

Aim for at least two advantages and two limitations. Think about data quality, complexity, and interpretation.


Module 6 — Quick Reference
P50
50% confidence — project likely as not to finish by this date. Not a commitment date.
P80
80% confidence — the common benchmark for infrastructure programme commitments.
Merge Bias
CPM underestimates programme duration because parallel paths converge — any path can slip and delay the merge event.
Contingency
P80 date − deterministic finish date. Held as a single activity before the finish milestone.