Module 4 Quiz: Earned Value Management

Module 4 Quiz — Earned Value Management

This quiz covers the core concepts from Module 4. Questions 1–5 are multiple choice — select the best answer. Questions 6–9 are short-answer and calculation — work through your answer first, then reveal the model answer.

Score tracker: 0 of 5 multiple choice answered

Part A — Multiple Choice

Q1. What metric in EVM compares the value of work completed to the budgeted cost for that work?

Q2. A project with a CPI of 1.1 indicates:

Q3. What is the main purpose of Earned Value Management?

Q4. Earned Value (EV) is calculated by:

Q5. A positive Schedule Variance (SV) signifies:


Part B — Short Answer & Calculation

Work through your answer before revealing the model response. These questions are not auto-marked.

Q6. Briefly explain the difference between CPI and SPI.

Think about what each index measures before revealing the answer.

Q7. Describe two benefits of using EVM in project management.

There are four covered in the lesson — name two with a brief explanation of each.

Q8. A project is at Week 10. The Planned Value (PV) for this point is $50,000, and the Actual Cost (AC) is $55,000. Calculate the Cost Variance (CV) and Cost Performance Index (CPI).

Assume the project is on schedule (EV = PV) unless otherwise stated.

Hint: CV = EV − AC  |  CPI = EV ÷ AC

Q9. Explain how a project manager can use EVM to identify potential problems and take corrective actions.

Think about what declining trends in CPI and SPI tell you, and what a PM would do in response.


Module 4 — Quick Formula Reference
SV = EV − PV
Schedule Variance (+ = ahead)
CV = EV − AC
Cost Variance (+ = under budget)
SPI = EV ÷ PV
Schedule Perf. Index (>1 = ahead)
CPI = EV ÷ AC
Cost Perf. Index (>1 = under budget)