Static Critical Path?

Not only can it change, it doesn't even have to be continuous from the start to the Project end.


Intermediate milestones and contractual obligations can create driving paths to & from these milestones, that may themselves represent critical paths.


Is the critical path different to what you expected? Perhaps it time to review the schedule logic & durations or it's time to change your expectation!



 
 
 